KYIV (QHA) -

Following the agreements reached between "Ukrenergo" and Crimean blockade participants, the company has started restoration works on 220 kV Kakhovskaya – Titan transmission power line, according to the "Ukrenergo" website.

- In spite of the difficult working conditions (rain, wind, soaked ground), Kherson backbone team of the State Enterprise "National Power Company" Ukrenergo " carried out a planned amount of works to restore the 220 kV Kakhovskaya – Titan transmission power line. The damaged power line was dismantled and replaced with a new one. The adjacent power lines have also been aligned and fixed. The works will continue Nov 25, according to a statement.

QHA